Home>Business Project>Vietnam Project

Project information
Investors : Taekwang Power Holdings Co., Ltd.
Investment Type : BOT (Build-Operate-Transfer)
Capacity : 1,200MW (2x600MW)
Commercial Operation Period : 25 years after COD
Commercial Operation Date : Dec 2020
Primary Fuel : Anthracite (Domestic Coal)
Location : Nam Dinh Province
  (about 90km southeast of Hanoi in Vietnam)

Project Advisors
 

Project Structure
 

Project Milestone
 
Data Project Milestone
Apr 2008 Approval of project site
Mar 2009 Approval of plan of construction and project development by MOIT
Dec 2010 Principles of Project Agreements Signed
Mar 2011 Confirmation of domestic coal supply by VINACOMIN
Dec 2011 KEXIM and K-Sure Support Letters
May 2012 Submission of BOT Contract draft
Jul 2012 EIA approval by MONRE
Sep 2012 Submission of LLA draft
Sep 2012 EPC Contractor tender and preliminary bid evaluation
Oct 2012 Approval of Feasibility Study by MOIT
Feb 2013 EPC preferred bidder selection
Apr 2013 Establishment of CSR Council
Apr 2013 Submission of PPA draft
Jun 2013 Submission of GGU draft
Sep 2013 Approval of Government to enter into one agreement with VINACOMIN for Coal Supply and Coal Delivery
Oct 2013 Submission of CSA draft
Oct 2014 Signed JDA(Joint Development Agreement) with ACWA power
Jan 2016 Investment Agreement Signing for Nam Dinh 1 BOT Project